Prime test and operations contractor Jacobs will perform the final checkout and integration of all flight hardware for Nasa’s Artemis I mission around the Moon.

Inspection and final processing activities include installing sensors on the motor segments of the solid rocket boosters (SRB) as part of its Space Launch System (SLS), integration and assembling.

Nasa took delivery of the motor segments of the SRB at the Kennedy Space Centre (KSC) in Florida, US, on 15 June.

The Jacobs team received the solid propellant-filled SRB hardware from Northrup Grumman (NG).

The segments will also be joined with aft exit cones to form aft assemblies for SRBs. These aft assemblies will then be stacked on the mobile launcher.

Jacobs Critical Mission Solutions senior vice-president Steve Arnette said: “The arrival of the SRB components means we are getting very close to the stacking of flight hardware in the iconic Vehicle Assembly Building (VAB) at KSC.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

“Once our team has conducted final inspections, processing and mating of the SRB segments, they will transport everything to the VAB for stacking to begin.”

On 24 June, Jacobs integrated the first of two SLS aft motor segments with the aft skirts at the Rotation, Processing and Surge Facility (RPSF) at the KSC.

Containing five solid fuel segments, each 177ft-tall SRBs will provide 3.6Mlb of maximum thrust for the SLS rocket.

Marking the first launch of SLS and Orion, Artemis is scheduled for launch next year.